# Orange Park's Johnson Slough project: a $14 million note, mitigation credits bought late, and a closing moved
- URL: https://www.readearlysignal.com/orange-parks-johnson-slough-project-a-14-million-note-mitigation-credits-bought-late-and-a-closing-moved/
- Published: 2026-11-12T13:40:38.000Z
- Updated: 2026-11-12T13:40:38.000Z
- Description: Orange Park approved borrowing about $14 million on split votes to rebuild the Johnson Slough crossings, bought wetland credits late and moved the loan closing.
- Author: John Cattano
- Tags: Clay County, Orange Park

Orange Park has approved borrowing about $14 million on split votes to rebuild the Johnson Slough crossings, and its permit depended on wetland credits bought at the last minute.

The design-build project replaces the Johnson Slough culverts and roadway crossings with three bridges.

On October 6 the Town Council set a guaranteed maximum price with Superior Construction Company Southeast, LLC, with substantial completion due January 31, 2028\. Approval was "contingent upon successfully obtaining the required permit from the St. Johns River Water Management District."

The same night it approved a capital improvement note with Webster Public Finance Corporation at a fixed 4.840% to 2046, with up to $7 million expected back from a Resilient Florida grant. Both votes were 3-2, according to the meeting's minutes.

Under Resolution 24-26, which authorizes the note, principal is due each October 1 starting in 2028.

On October 20 the Council voted 4-1 to add the contractor as a party with payment authority on agreements to buy wetland mitigation credits from two banks, and to let the town manager sign them. The meeting's minutes list the credit documents among the final requirements for the permit, and the contractor said it would pay under its contract, according to video of the meeting.

The agreements in the meeting packet price the credits at about $67,000 from the Normandy Mitigation Bank and $8,100 from the Star 4 Mitigation Bank. A second motion, reducing the contingency in Superior's contract by about $75,000 "for the mitigation credits," passed 3-2.

The loan closing could not happen on its original date of October 22 because "the 21-day public notice and appeal period for Sovereign Submerged Lands (SSL) runs through October 30," the minutes say, so it was set for October 29\. Town advisors said a delay into November could add roughly $427,000 in debt service, according to the minutes.

By the numbers: guaranteed maximum price about $14.0 million; maximum indebtedness about $15.9 million; Resolution 24-26, note about $14.0 million; mitigation credits about $67,000 (Normandy, 0.38 credits) and $8,100 (Star 4, 0.18 federal-only credits); contingency reduced by about $75,000.

What's next: construction, which the Council was told on November 5 is anticipated to begin in late January or early February. At that meeting the mayor said the St. Johns River Water Management District had issued the project's permit, according to video of the meeting. Early Signal has not obtained whether the loan closed on October 29.