Nassau's draft data-center rules: six size classes, separation of up to half a mile, and no tax breaks

Nassau County's data-center study committee has published draft rules with six size classes, separation of up to half a mile and no tax breaks.

Nassau County's data-center study committee has published draft rules on where data centers can go, how big they can be and who pays for the power lines.

The committee, made up of County staff and set up by the County Commission on May 20, released its draft report and draft regulations on October 21. The County says the findings "are not considered adopted policy."

The rules would sort data centers into six classes by floor area or electrical load. They run from a small building to a "mega campus" of more than 3 million square feet or more than a gigawatt, which would need its own planned unit development zoning, a PUD. In the draft's chart, a "Server Room" column beside the six classes is marked "Not a Data Center, less than 1,000sf".

Large facilities and campuses would be limited to industrial land of at least 200 acres inside a Vision 2050 employment center, or to a new data-center district within 3 miles of the 500-kilovolt transmission line. Data centers would be barred from every residential and agricultural district.

Separation from residential buildings, schools, churches and daycares would run from 100 feet for the smallest class to 2,640 feet for a mega campus, kept forested.

The draft also sets noise limits, with daily fines for late noise-monitoring logs and reporting outages. It requires closed-loop cooling and underground new distribution lines, and a fire station if none is within 5 miles. It bars County non-disclosure agreements.

The report recommends no property tax abatement and developer-paid infrastructure. It also recommends a resolution removing data centers as a target industry for County incentives.

The draft contradicts itself in six places. Among them is the floor-area floor for the large class, which is 150,000 square feet in one section and 100,000 in another.

At the County Commission's October 26 workshop nothing was adopted and no vote was taken. A speaker said the sound appendix will probably change significantly and that the enforcement provisions will be gathered into one subsection, according to video of the meeting.

At its second workshop, on November 9, the Commission again adopted nothing and took no vote. The board was told the committee had been asked to bring back public policy to govern data center development, according to video of the meeting.

After public comment, a commissioner asked whether the question could go to voters in a referendum. County Attorney Denise C. May said the question was new and needed legal research before she could give the board a full answer. Commissioner John F. Martin proposed one more workshop for that research, and the board agreed. The County Attorney also said that extending the moratorium indefinitely would not be constitutional. She said that even if the question went to voters and they barred data centers, the County could still face lawsuits, according to video of the meeting.

A moratorium adopted in June stays in force in the meantime.

By the numbers: Ordinance 2026-044 (moratorium, up to 12 months); small class 20,000 sq ft or less and 5 megawatts or less; noise 65 and 55 decibels; monitoring fines $1,000 a day; comment open to January 8, 2027.

What's next: another workshop, which the board agreed on November 9 to hold, according to video of the meeting. County documents for the workshop listed public hearings on December 1 at the Planning and Zoning Board and on December 14 and January 25 at the County Commission, and a final report "before the Thanksgiving holiday". At the workshop, the chair said the Planning and Zoning notice would need to change, and County Manager Taco Pope said that would reset the schedule. Public comment is open until January 8, 2027, according to county documents.