Green Cove Springs moves to the last piece of a 13-year sewer consolidation

Green Cove Springs has moved to the last piece of a 13-year sewer consolidation, a pipe under Governors Creek.

Green Cove Springs moves to the last piece of a 13-year sewer consolidation

Green Cove Springs has moved to the last piece of its sewer consolidation: a pipe under Governors Creek that lets the city close its south plant.

The project, Harbor Road Phase III, lays a 16-inch force main from Lift Station No. 2 at the south end of Palmetto Avenue, drilled under Governors Creek to the Harbor Road Water Reclamation Facility. Every lift station in the south service area will be redirected, and the South Wastewater Treatment Facility will be decommissioned with its permit kept active. At the October 20 meeting Water Utilities Director Scott Schultz described it as the last piece of a 13-year effort; the same presentation tied it to the state law ending discharge of treated effluent to surface waters, according to video of the meeting. City staff wrote that the law requires utilities to end those discharges by 2032. The project will "provide approximately 10 years of additional treatment capacity," according to the May 19 minutes. The force main's contractor is Badger Drilling, LLC, at a contract price of about $2.8 million. Its first pay request, about $60,000, "primarily encompasses mobilization," staff wrote.

The Harbor Road plant that will take the flow, a 1.25 million-gallon-a-day advanced wastewater treatment plant, came online in 2025, after its contractor "abandoned the site and filed bankruptcy" in 2023, according to city records. The contractor's surety then hired Sawcross Inc. to finish it. The cost to complete rose from about $2.6 million to about $4.7 million, and the surety paid the city about $2.1 million over the original contract price, staff wrote. The plant's staff won a 2025 state operations award for keeping the plant running through the stoppage, TPO magazine reported.

State revolving fund loans pay for it, with large shares forgiven. The Phase III loan agreement of about $8.7 million has about $7.0 million forgiven, leaving an actual loan of about $1.7 million. The Council approved the Phase III loan agreement 4-1 on May 19, with Council Member Tom Centracchio voting no, according to the meeting's minutes. A separate water loan funds North Grid and Harbor Road water plant upgrades. Council approved the construction contract with PBM Constructors, Inc. on the October 20 consent agenda, according to video of the meeting and the city's online recap, which reported a 5-0 vote. The staff report gives the agreement as about $3.3 million and its fiscal impact as about $3.7 million from the Water Fund's capital budget.

Staff wrote that Reynolds Industrial Park "has significant potential for a variety of development types," and the Public Works report says future plant phases are "determined by growth." The city's report says the south plant "could be re-commissioned later depending on future activities at the Reynolds site," and its capacity figures carry the note "No Reynolds growth or loading projections included in above."

By the numbers: $8,742,000 (Phase III loan agreement); $7.0 million forgiven, $1.7 million actual loan; water loan about $5.35 million, $1.6 million forgiven, at 1.46% over 20 years; PBM contract about $3.3 million against about $3.7 million from the Water Fund's capital budget.

On November 10 the Council approved the contractor's first pay request on its consent agenda, according to video of the meeting. The same vote approved a state grant of about $1.3 million and a reclaimed-water agreement with the Clay County Utility Authority.