# Fernandina's waterfront: a $12.6 million marina rebuild and the first seawall segment
- URL: https://www.readearlysignal.com/fernandinas-waterfront-a-12-6-million-marina-rebuild/
- Published: 2026-11-12T20:16:26.000Z
- Updated: 2026-11-12T20:16:26.000Z
- Description: Fernandina Beach approved a marina redevelopment of about $12.6 million and the first segment of its downtown resiliency seawall, with mobilization set for November 16 as the Commission was told.
- Author: John Cattano
- Tags: Nassau County, Fernandina Beach

Fernandina Beach has approved the redevelopment of its harbor marina and the first segment of its downtown resiliency seawall.

On July 21 the City Commission approved Resolution 2026-92, awarding Invitation to Bid 26-10 for the Fernandina Beach Marina Redevelopment to Baker Consulting & Engineering, LLC dba Baker Design Build. The base bid is about $9.7 million, and the resolution authorizes a project cost of about $12.6 million.

The scope includes demolition of structures in the project area, dredging, replacement of sections of seawall, an over-water pier, dock components, and water, sewer, electrical and fueling components.

City staff wrote that the existing marina seawall is "approximately 100 years old" and that "The now vacant restaurant has a deteriorating foundation and a piling system that has been falling into the river, causing safety and water flow problems."

Staff recommended transferring up to $4 million in fiscal year 2025/2026 from the Capital Improvement, Community Redevelopment Area, Marina Operations and Paid Parking Revenue funds and a Pinnacle Bank line of credit. Staff also wrote that the Commission reached consensus at a July 7 workshop to give the City Manager about $1.3 million in contingency spending authority.

On June 2 the Commission adopted Resolution 2026-71, a supplement to the City's 2005 waterfront community redevelopment plan. Its list of candidate projects includes a "Fernandina Beach Marina Redevelopment (Brett's Demolition and Replacement)."

The resolution also added Brett's Waterway Cafe to the plan's marina objective. The objective says redeveloping the marina and the cafe to ease siltation and deteriorating site conditions could help address blight and spur change in the redevelopment area.

A separate Harbor Master Plan is still in draft. Its first phase, prepared by Moffatt & Nichol and dated September 14, covers the waterfront north of Centre Street. A second phase, if authorized, would include the marina, the draft says.

Demolition of Brett's began in late October as part of the city's marina redevelopment, Early Signal observed.

The City has also moved on its downtown seawall. On July 7 the Commission approved an application to the state's Resilient Florida program for downtown seawall construction, amended to request $1.5 million. Staff said about $2 million is needed to complete the seawall.

On August 4 the Mayor read a proclamation recognizing Florida Senator Clay Yarborough and Florida House Representative Dean Black "for their successful efforts in securing $2,000,000 in legislative funds for downtown seawall construction."

On September 15 the Commission unanimously approved Resolution 2026-126, awarding Invitation to Bid 26-11, "Waterfront Resiliency Segment One," to Earth Tech Enterprises Inc for about $1.2 million. The same night it approved Resolution 2026-127, work orders with Passero Associates, LLC for the design, engineering, permitting and bid services for demolition of the Amelia Riverfront Restaurant, in an amount not to exceed $274,450.

By the numbers: Resolution 2026-92, about $12.6 million; Resolution 2026-126, about $1.2 million; Resolution 2026-127, not to exceed $274,450; a transfer of up to $4 million.

What's next: Segment One's contractor is set to start November 16, according to video of the October 20 meeting.