Baker County's lot pipeline: three subdivisions and a rezoning through the planning board

Baker County's planning board approved Kings Manor Phase 4, Macclenny II Unit 4 and Camryn Crossing's added lots, and the County rezoned Cypress Home Builders' 41 acres for five-acre lots.

Baker County's lot pipeline: three subdivisions and a rezoning through the planning board

Baker County's Land Planning Agency voted this year to approve three single-family subdivisions and recommended a rezoning that could lead to a fourth. One of the three is a change adding lots to an approved plan.

According to the board's minutes, "Subdivision and replat applications are under the final authority of the LPA unless an exemption is requested," and "Subdivisions stop with the LPA unless there is a companion variance or exemption." The County Commission nonetheless also heard and approved one of the three, Camryn Crossing, with no exemption or variance before it.

Kings Manor Phase 4. Rock'N Lee LLC, through Jeremy Lee, proposes 47 lots of at least half an acre off County Road 127 and Dolphin Court (parcel 01-3S-20-0000-0000-0186), each on a private well and septic system. Dolphin Court would be "completed with asphalt pavement."

It is the fourth and final phase of a master plan approved in 1995. That plan proposed 85 lots, and "the final development will only contain 79 lots," the staff report says. The Land Planning Agency voted to approve it on September 10.

Macclenny II, Unit 4. Knabb Lands Inc, through George Knabb Jr., proposes 35 lots east of Crepe Myrtle, west of Raintree Dr. and north and south of Hickory St. in Macclenny (parcel 09-3S-22-0000-0000-0010). They are 17 of about an acre, nine of five acres or more and nine of ten acres or more.

The County Manager's comment raises existing drainage issues in Macclenny II and the cumulative effect of adding more lots while the community relies on a single primary access point to State Road 121. The item was deferred on August 13, and the Land Planning Agency voted to approve it on September 10.

Camryn Crossing. North Star Acquisitions LLC, through David Burnham, asked to change a subdivision approved in June 2025 from 55 to 67 lots of at least a quarter acre. The subdivision covers about 27 acres at the northeast corner of County Road 125 and County Road 139B (parcel 36-2S-21-0000-0000-0030). The change is sought because the wetland in the southwest corner "is smaller than what was initially anticipated."

The lots would take water from the Town of Glen and use private septic systems. The Land Planning Agency voted to approve the change on July 16, and the County Commission approved it unanimously on August 4.

Cypress Home Builders. The County rezoned about 41 acres off Reid Stafford Rd / Glen Nursery Rd, a portion of parcel 11-3S-21-0000-0000-0010, from Agriculture 7.5 to Agriculture 5. The rezoning is for a possible subdivision of about eight lots of five acres or more.

The Land Planning Agency recommended approval on September 10, and the County Commission approved Ordinance 2026-27 unanimously on October 6. Any subdivision would need its own application.

By the numbers: 47 lots at Kings Manor; 35 at Macclenny II; 67 at Camryn Crossing, up from 55; about eight on the Cypress land. Kings Manor 32.84 acres, 31.09 of them to be developed; Macclenny II about 190 acres.

What's next: the final plats. For Macclenny II the staff report notes that any outstanding St. Johns River Water Management District or other state permits must be satisfied before platting.

Corrections policyReport an errorShare on LinkedIn